Over the past two months, the Town and its contractors have been busy at the future Irondequoit Community Center.
MAY, 2020: The vast majority of the interior demolition of the Town’s 44,000 square foot space has been completed. All of the partition walls, overhead HVAC, electrical and plumbing have been demolished and removed. At this time the Town’s general trades contractor Javen Construction has commenced the demolition of concrete floors to make way for the gymnasium and are poised to commence the demolition of some interior structural steel.